Permanente Quarry: Reclamation Plan Amendments
2019 Reclamation Plan Amendment for Quarry Expansion (File PLN19-0106)
Project Description:
On May 22, 2019, Lehigh submitted an application to replace their 2012 Reclamation Plan. This proposed Reclamation Plan Amendment would complete replace the existing Reclamation Plan, and includes the following significant modifications:
- Retain in place the overburden material currently stored in the West Materials Storage Area (“WMSA”) rather than use it to backfill the main quarry pit. Instead Lehigh proposed to backfill the pit with clean fill (approximately 20 million cubic yards) which will be trucked in from off-site. This would require approximately 600 new truck trips per day, five days a week for the next 30 year, depending on available supply.
- Decrease the lower ridge crest along a portion of the North Quarry highwall by approximately 100 feet, necessitating modification of the 1972 Ridgeline Protection Easement held by the County.
- Expand the reclamation plan area by 73.4 acres, increasing the total reclamation plan area from 1,238.6 acres to 1,312 acres. Additionally, the operator proposes to expand mining activities into a new 30-acre area, referred to as the “Rock Plant Reserve”.
- Use an existing Pacific Gas & Electric, Co. utility access road, or establish a new haul road between Leigh and Stevens Creek Quarry (“Utility Haul Road”)*.
- Reclaim an approximately 3,600-foot segment of the existing Plant Quarry Road and adjacent areas.
*This aspect of the project was proposed under the separate Utility Road Reclamation Plan Amendment Application, File No. PLN19-0067, which has been withdrawn and incorporated into PLN19-0106.
Project Status:
Lehigh’s proposed Reclamation Plan Amendment (RPA) is currently undergoing environmental review through the preparation of an Environmental Impact Report (EIR). The County is currently in the process of finalizing the scope and bid for the EIR. Once the scope and bid have been finalized, the County will prepare and circulate a Notice of Preparation (NOP) and post the NOP to the project website. The County provides periodic updates to interested members of the community. If you are interested in receiving information from the County about this project, please consider signing up to be added to the Lehigh Interested parties list.
Project Materials:
- Pre-Application Forms
- Pre-Application Response Letter (submitted May 17, 2019)
- Application Forms (submitted May 22, 2019)
- Submittal Letter (submitted May 22, 2019)
- Project Description and Environmental Information (Binder 2) (submitted May 22, 2019)
- Reclamation Plan (submitted May 22, 2019)
- 30-day Extension (submitted June 21, 2019)
- Incomplete Letter (submitted July 22, 2019)
- Quarry Response to Incomplete Letter (submitted September 30, 2019)
- Quarry Response to Incomplete Letter (submitted October 10, 2019)
- Complete Letter (submitted November 8, 2019)
- Appeal to State Mining and Geology Board (submitted November 22, 2019)
- State Mining and Geology Board Response to Appeal (submitted March 11, 2020)
- RPA Status Request (submitted February 24, 2020)
- County Response to Quarry Letter from February (submitted March 13, 2020)
- County requesting understanding from Quarry (submitted March 13, 2020)
- Lehigh Application Status Request (submitted March 24, 2020)
- Proposed Processing Schedule (submitted March 2020)
- Lehigh Application Status Request (submitted June 25, 2020)
- County's Response (submitted August 5, 2020)
- Off-Agenda Memo to Board of Supervisors (August 5, 2020)
- County Response to Lehigh Data Request (September 18, 2020)
- Lehigh Letter to Planning Director (October 28, 2020)
- Lehigh Letter to Planning Director (November 13, 2020)
- Off-Agenda Memo (December 21, 2020)
- County Response to Lehigh (December 29, 2020)
- Lehigh Letter to County (October 15, 2021)
2019 Reclamation Plan Amendment for Utility Road (Superseded/combined with PLN19-0106)
- Application Forms (3/26/2019)
- Submittal Letter (3/25/2019)
- Reclamation Plan Amendment (3/26/2019)
- Incomplete Letter (4/29/2019)
- Response to Incomplete Letter (7/12/2019)
- Complete Letter (8/29/2019)
- Supplemental Information from Lehigh (10/01/2019)
- County Request to Consolidate with PLN19-0106 (2/13/2020)
- Response to County Request to Consolidate with PLN19-0106 (2/24/2020)
- Request to Consolidate with PLN19-0106 (3/24/2020)
2018 Minor Reclamation Plan Amendment for Haul Road - Superseded
- Application Forms
- Reclamation Plan Amendment
- Sheets 1 through 3 – Rock Plant Haul Road Conceptual Design, Sections, and Reclamation Plan
2013 Reclamation Plan Amendment - Withdrawn
2012 Reclamation Plan Amendment for Permanente Quarry
- Conditions of Approval (June 2012)
- 6/26 Appeal to the Board of Supervisors and Related Documents
Includes links to report, attachments, correspondence, and transcripts. - 6/7 Staff Report for Planning Commission and Related Documents
Includes links to report, attachments, correspondence, and transcript. - 5/31 Staff Report for Planning Commission and Related Documents
Includes links to report, attachments, correspondence, and transcript. - 5/24 Staff Report for Planning Commission and Related Documents
Includes links to report, attachments, correspondence, and transcript. - Final Environmental Impact Report and Appendices
- Draft Environmental Impact Report
Includes draft EIR and public comments received.
2011 Reclamation Plan Amendment for Permanente Quarry (File No. 2250-13-66-10P/M1)
- Notice of Preparation Scoping Comments
- Notice of Preparation Scoping Meeting Presentation
- Notice of Preparation of an Environmental Impact Report for the Reclamation Plan Amendment (consolidated) for Permanente Quarry.
- Notice of Availability
- Draft Environmental Impact Report
- This Applications supersedes the Permanente Quarry Comprehensive Reclamation Plan Amendment submitted in 2010 and the East Material Storage Area (EMSA submitted in 2009. It consolidates the prior applications in to one project area and eliminates the proposed second mining pit area.
- Reclamation Plan Amendment (updated 12-13-11)
- Attachment A - Legal Description
- Attachment B - Revegetation Plan
- Attachment C - Geotechnical Report
- Attachment D - Biological Resources Assessment
- Attachment E - Hydrological Investigation
- Attachment F - Drainage Report
- Attachment G - Water Quality Analysis
- Attachment H - Air Quality Technical Analysis
- Attachment I - 1985 Reclamation Plan
- Attachment J - Best Management Practices for Boulder Removal
- Engineering Drawings and Details
- Interim Financial Assurance Cost Estimate
2010 Reclamation Plan Amendment for Permanente Quarry - Superseded (File No. 2250-13-66-10P)
Lehigh applied for an amendment to the 1985 Permanente Quarry Reclamation Plan.
- Reclamation Plan Amendment Application
- Reclamation Plan Amendment - Volume I
- Main Document - May 2010
- Attachment A - Legal Description
- Attachment B - Revegetation Plan
- Attachment C - Geotech Report
- Attachment D - EMSA-CMSA Geotech Report
- Attachment E - Biological Resources Assessment
- Attachment F - Hydrological Investigation
- Attachment G - Drainage Report
- Attachment H - Water Quality Analysis
- Attachment I - Noise Report
- Attachment J - Air Quality Analysis
- Attachment K - Archeology
- Attachment L - 1985 Reclamation Plan
- Attachment M - RPA for EMSA June 2009
2009 Reclamation Plan Amendment for Permanente Quarry - East Materials Storage Area (File No. 2250-13-66-09P)
Lehigh (Hanson) applied for an amendment to the 1985 Permanente Quarry Reclamation Plan to include an approximately 89-acre area to be used for overburden storage identified as the East Materials Storage Area (EMSA). This amendment proposes to place approximately 6.5 million tons (approximately 4.8 million cubic yards) of overburden fill over an approximately six-year period.
2007 Reclamation Plan Amendment for Permanente Quarry (File 2250-13-66-07P)
The Permanente Quarry Comprehensive Reclamation Plan Amendment, submitted in 2007, has been superseded by a revised application submitted on May 28, 2010. This application can be viewed at the County Planning Office.